Browse through the details of our diverse client list.

ServiceOntario, Brampton Centre

ServiceOntario is the retail face in service delivery on behalf of individuals and businesses in Ontario. Routine transactions are completed through ServiceOntario centres and their website.

The interior fit out of their new Brampton Centre began in base building condition. Our scope included the construction of new drywall partitions and ceilings, an open ceiling systems, new doors & frames, millwork, barrier free washrooms, flooring, tile, HVAC, plumbing, communications and new security system.

CityBrampton

Budget< $1,000,000

Sq Ft12,500

Completion2012

Duration14 Weeks

Design ConsultantNORR Ltd.

OwnerMHPM Project Managers Inc.

Contract TypeLump Sum

PROJECT CHALLENGES

  1. Scope changes for communications cabling caused project delay
  2. Open cell ceiling tiles had a long lead time

OUTCOME

To mitigate some of the issues with working in a post and beam building, Flat Iron performed its own site survey to assess differences in heights and levels to assist in establishing a micro schedule to circumvent delays with lead times. Open cell ceiling tiles were installed post move-in with no interruption to client. In the face of project delays the client’s moved-in date was still met.